Kenya’s state power producer KenGen has finished rehabilitating Olkaria I, its oldest geothermal plant, raising its capacity from 45 to 63 megawatts (MW), Managing Director Peter Njenga said on 25 November. The three-year works cost over 15 billion shillings (about $116 million) from development partners, and the plant is in trials before President William Ruto commissions it on 7 December. Olkaria I, near Naivasha, has produced power since the 1980s, while Kenya’s peak demand has risen to 2,559 MW from 2,135 MW four years ago, according to the energy ministry. The extra 18 MW of round-the-clock geothermal power eases pressure on a grid that has started testing 350–400 MW of imports from Ethiopia to cover low-wind periods.